With the Christmas holidays approaching, the RG Wembley Team are arriving at the landmark stage of 1 year on site. There has been much progression with the RC-frame, which is currently at the seventeenth floor, one more floor to go before topping out in January 2016.
The internal fit out works are coming along in leaps and bounds, with lower levels finalising second fixing and rooms starting to take shape ready for finishing trades. The external glazing installation and continued curtain walling on the external envelope is transforming the building on a daily basis.
As we enter 2016, we will be undertaking ground works again as we commence construction of the two retail units. We will also see finishing trades on site, along with roof and secondary steelwork installation. Not long after, bedroom and kitchen furniture fit out is due to commence in February.
As we reflect on where we were a year ago, the progress on site has been fantastic, a credit to the whole Wembley Team.