Waitrose, Front of Store Roll Out

Light touch refurbishment projects over 40+ stores in an 18 month duration including:

1. New welcome desks inc coffee offer
2. New Self checkouts
3. Refrigeration Moves
4. E Commerce (Click and Collect) projects
5. Minor refurbishments of toilets, front of shops inc relaying of sales floors to suit.

Generally very simple projects with the focus on detailed process, strong leadership and excellent communications with each store to ensure that stores are complete and snag free in one hit. Managed by a very small team within RG with a retail background rather than construction background as the focus is on project phasing and understanding retail operation.

Employers Agent:

Underwood Carpenter

PQS:

Underwood Carpenter

Completion Date:

Various

Project Timescale:

68 weeks