This Design and Build scheme comprised three new retail units totalling 3,882 m2 including a mezzanine with a new rear service yard, a 112 space customer car park and new services.
Refurbishment of the existing Unit 1 included the provision of additional mezzanine capacity, improved and expanded servicing arrangements, demolition of the existing compound to increase staff parking, revised pedestrian ramp and step arrangement to the South of the site and an improved road junction.
The project had 4 Sectional Completion dates for various tenants including; M&S, Maplins, Currys and Dunelm. Compliance with Tenant and Employers requirements was key along with co-ordination of novated design team and getting design to construction status including utilities.
Air test of less than 3 were achieved for all buildings and EPC’s ratings of B achieved. BREEAM targets were – Unit 1A Excellent targeted; Unit 1F Dunelm Very Good targeted.