RG Group were appointed to fit out a new 360,000 sq ft Regional Consolidation Centre (RCC) for B&Q in Swindon.
The works consisted of the installation of all mechanical handling equipment and associated works such as floor levelling, VNA guidance, charging areas, colleague meeting zones, sprinkler system, extract systems, installation of new coldrooms and alterations to the colleague rest areas. The scope of works also includes the construction of new high bay racking which included sprinklers, signage, bar coding and floor lining.
External works included Armco and column protection, bay lining and numbering, external signage and a weighbridge.
Following the works to the new RCC and the transfer of the stock to the new facility, we undertook additional fit out works within the existing distribution centre building.
These works includes some high bay racking reconfiguration (including associated services such as sprinkler and lighting modifications).