Unite Wembley – December Progress Update

With the Christmas holidays approaching, the RG Wembley Team are arriving at the landmark stage of 1 year on site.  There has been much progression with the RC-frame, which is currently at the seventeenth floor, one more floor to go before topping out in January 2016. The internal fit out works are coming along in […]

Unite Wembley Mains Power is Live!

The Unite Wembley team are pleased to announce that mains power is now live for the scheme.  This is a great achievement, undertaken in less than 11 months into the build, with 10 months left until completion. The delivery of STATs are always a key risk, with high influence on successful project delivery.  They remain […]

Unite Wembley Comms Secured

Taking a leading role, but working collaboratively in close partnership with Unite’s IT department, and managed service provider Cablecom – the RG Wembley team is pleased to announce that Copper and Fibre communication, has been successfully secured for the scheme. This early delivery reflects our continued approach to deliver project STATs at the earliest opportunity.

Unite Wembley Blog Launch

As we enter October 2015, we have been on site for 9 months having commenced works in early January 2015.  Within this period, 748 piles have been installed, the ground floor slab completed, and the concrete frame is currently at the 12th floor (6 more to go!).  Internal fit out works are firmly underway, (M&E, […]